Originally scheduled for commissioning in mid-2010, the Northern Sewerage Project will now be ready for use in early 2012, according to Victorian State Water Minister Tim Holding.

“This project is being delivered on budget and six months ahead of schedule,” Mr Holding said.

Victoria the tunnel boring machine (TBM) completed a 1.3 kilometre tunnel after breaking through a shaft in Coburg in late-February. Victoria has been excavating 24 hours a day, six days a week since December and has created a three metre diameter tunnel, approximately 30–40 metres below the surface.

Victoria is just one of three TBMs currently working on the Northern Sewerage project. Julia the TBM commenced her tunnelling activities in January 2009, whilst Gemma started tunnelling May 2008. Contractor John Holland has been working on the project since 2007.